Moving dirt without the right paperwork in place costs operators thousands — in fines, stop-work orders, and delays at TCEQ final inspection. After handling registration for 50+ Texas UST sites, here's what needs to be done before the excavator shows up.

Phase 1: Before You Submit Anything to TCEQ

Owner / Operator Verification

Contractor Verification

Phase 2: TCEQ Notification (30+ Days Before Installation)

Form TCEQ-0762 Package

Common rejection reason: The installer's TCEQ certification number is missing or expired on Form 0762. TCEQ returns the form and your 30-day clock doesn't start until they receive the corrected version. This alone adds 2–3 weeks to many projects.

Phase 3: Site Prep Verification

Before Excavation Begins

Phase 4: Installation Inspection Hold Points

TCEQ requires inspections at specific milestones. Do not proceed past these points without inspector sign-off:

Hold Point 1 — Before Backfill

Hold Point 2 — Piping Pressure Test

Hold Point 3 — Final Commissioning

Phase 5: Final Registration Package

Documents to Submit to TCEQ

Stealth Tanks manages this entire process for all turnkey installations. We've never had a site fail TCEQ final inspection. If you're managing a project yourself, print this checklist and go through it line by line — the issues that cause rejections are nearly always the small documentation items, not the physical installation.

Questions about your specific site? Call 346-209-2032